The Challenge:

AsBuilt was contracted to capture the head chutes, flop gate, load zones, drives, and interconnecting chute work of coal handling system.  This system has been in operation for decades with multiple upgrades and changes since the original installation.   This system was underground in difficult to access area. 

 

The Solution:

The solution was to scan and model the existing equipment arrangementThe 3D model was used as the design background for the future design and to place updated equipment. 

Deliverables:

  • Point Cloud 
  • 3D Modeling 
  • Clash Detection 
  • 3D Design Backgrounds