AsBuilt for Data Center Structural Steel

The Challenge:

Confirm the structural steel was installed according to the construction plans.   

The Solution:

The only way to confirm the exact placement of the members was to scan the as built and overlay the design drawings.   All deviations were easily documented, and changes were made to the as built drawings. 

Deliverables:

  • Point Cloud 
  • 3D Modeling 
  • Deviation Reporting for Red Lines