The Challenge:
AsBuilt was contracted to resolve flow complications in the limestone storage silos at a Power Plant, impacting the limestone feeders' operational performance and reliability. The plant also faced issues with the feeder discharge to the Ball Mill inlet chute.
The Solution:
AsBuilt collected comprehensive 3D laser scan data of the limestone storage silos and surrounding areas to create an accurate digital representation of the existing conditions. This scan data was used to develop precise 3D models, which provided the foundation for understanding the flow dynamics and identifying potential improvements. The models were then used for analysis, ensuring that all modifications were based on accurate, as-built data. The resulting models were reviewed and field-checked to ensure they aligned with the real-world conditions and were used to guide the creation of fabrication drawings and implementation plans.